INDOPOX, INDUSTRIAL GRADE FLOOR EPOXY APPLICATION METHOD
PREPARATION:
- Concrete needs at least 28 Days to be fully cured.
- Etch the floor or Grind it.
- To acid wash, Dilute one third Hydrochloridric acid with water,
- Add Acid to the water tank,
- Pour on floor, Use broom to spread it out,
- Wash it by high pressure washer after 5 Min.
- Apply PRIMIT when the floor is dried, Use 12 mm nap roller.
- Follow the ratio, Mix thoroughly by Mixer, Pot life two hours,
- Cut edges and corners first.
- EPOXY PRIMER, Needs to be applied on bare concrete as a thin layer to penetrate and needs 8 hours to dry.
- Inspect the floor, Needs to be dried.
- Patch Cavities and Cracks by Builderpox.
- Apply First Coat by roller, Use 12 mm nap roller
- Follow the ratio, Mix thoroughly by Mixer, Pot life 30 Min,
- Mix Small Batch, Use Scale, Mix by Weigh not Volume.
- Cut edges and corners first.
- Pour on Floor, Use Squeege to spread it out, apply by 270 mm roller, Check not to leave any line behind. Needs 8 hours to walk on.
- Apply Second Coat by roller, Use 12 mm nap roller
- Follow the ratio, Mix thoroughly by Mixer, Pot life 30 Min,
- Mix Small Batch, Use Scale, Mix by Weigh not Volume.
- Cut edges and corners first.
- Pour on Floor, Use Squeege to spread it out, apply by 270 mm roller, Check not to leave any line behind. Needs 24 hours to walk on.
- Needs 7 days to fully cured
- Do not wet the area at least for seven days depends on the weather condition.